Project Background & Objectives
In Avignon, ECOOR delivered the refurbishment of Hôtel Le Paradou as part of a comprehensive upgrade programme that elevated the property from a three-star to a four-star hotel.
The project was carried out in carefully planned phases, allowing the hotel to remain fully operational throughout the works. The first phase focused on refurbishing the guest rooms, followed by a second phase dedicated to the lobby and reception areas.
The objective was to enhance the guest experience while maintaining the right balance between comfort, functionality and the hotel’s identity.
The Client’s Brief
The client wanted to reposition the hotel through a carefully planned upgrade that would meet today’s hospitality standards while enhancing guest comfort.
The project aimed to refurbish the existing guest rooms, modernise the shared spaces, and support the hotel’s transition to a higher category, all while allowing the establishment to remain fully operational throughout each phase of the works.
The challenge was to transform the hotel progressively without disrupting its day-to-day operations.
Project Constraints
- Works carried out in an occupied hotel while maintaining normal operations throughout the project.
- Carefully phased construction programme designed to minimise disruption to the hotel’s day-to-day operations.
- Coordination of all works within areas welcoming guests on a daily basis.
- Maintaining an appropriate level of comfort for guests throughout the construction period.
- Careful programme management to support the hotel’s progressive upgrade to four-star standards.
The Outcome
Today, Hôtel Le Paradou offers modernised spaces that provide greater comfort and fully reflect its new four-star positioning.
The refurbishment of the guest rooms and reception areas has created a smoother, higher-quality guest experience while preserving the warm character that defines the hotel.
A carefully phased project, where every stage struck the right balance between construction works, ongoing operations and the quality of the guest experience.
Project Duration
3.5 months to refurbish the guest rooms, delivered on schedule and in line with ECOOR’s quality standards.
2.5 months to transform the lobby and reception areas, delivered on schedule and in line with ECOOR’s quality standards.